South Medford High School

Estimated Construction Dates: Summer 2008-August 2010
Last Updated on 9-26-08


 
PROJECT SUMMARY:

The current school was built in 1931 and has had multiple additions.  These additions have made the facility inefficient for the student population that attends.  The current campus has 78 classrooms on its 21 acre campus.  The new SMHS will be built at Cunningham and Columbus on approximately 38 acres, already owned by the district.  The new school will have 85 classrooms and offer 255,000 square feet of teaching space to accommodate 2,000 students.  The student parking entrance will be on Columbus Avenue and exit will be on Diamond.  Bus drop off will be between sports fields and student parking.  Faculty and visitor parking entrance will be on Cunningham Avenue.
The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

Click Here to view current  elevation and building plans here.  (Subject to change.)

Information about the new South Medford High School Facility--4/7/08

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: DayCPM www.daycpm.com
 Architect: Mahlum Architects www.mahlum.com
 Contractor: Hogan Construction www.hoganconstruction.com

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-6/30/08
$80,600,000 (GMP Accepted 7-1 by School Board) $4,280,441
Click here to see the monthly expenditures report.
Due to the closing out of the fiscal year, new total expenditures through September 08 will be reported mid-October.


Project Description & Status :

Project: Status
Medford Planning & Zoning Commission approved the zoning change from County RR-5 to Residential SFR-6.  The city of Medford does not have a school zone, so in order to build a school at the site the property must be zoned residential and MSD will have to apply for a Conditional Use Permit.  MSD has no intention of building single family residential homes on the site. Complete
MSD will host a meeting to present the results of the Traffic Study Complete
Conditional Use Permit Granted Complete
Groundbreaking Complete
MSD will host a updates/safety presentation for neighbors Complete
Guaranteed Maximum Price accepted Complete
Wetlands permit issued from the Department of State and Lands Complete
Army Corps of Engineers permit issued Complete
Put all fencing in place Complete

The footings have been completed in the front entry area and they are preparing to pour the footings in the classroom wing.  Excavating is taking place in the gym area. Underground utilities, such as the sewer main etc., are being put in place as well as preparation for the parking lot.  The project is currently on time and on budget. 

Current


PROJECT PHOTOS:
 

Land that school will be built on

Groundbreaking June 2, 2008 

 
Excavating etc.