Jackson Elementary School

Estimated Construction Dates: Summer 2008-2009
Last Updated on 3.12.09
View the new Progress Videos Page


 
PROJECT SUMMARY:                                                                                       

Jackson Elementary School was built in 1911 and has 23 classrooms on its 6 acre campus.  It was vacated due to structural concerns in 2007.  Kindergarten through 3rd grade were relocated to Westside, a former school owned by the school district. Fourth through 6th grade have been relocated to McLoughlin Middle School.  Opsis/Abell architects are moving forward with the redesign phase and the project will be bid in late Summer 2008.
The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

Opsis/Abell presentation given at the January 8th School Board Meeting

Limited Exterior Masonry Assessment--Jackson Elem 4-15-08

View the drafted floor plans for the new building

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: Steve Ennis  
 Architect: Opsis/Abell Architects www.opsisarch.com
www.abellarchgroup.com
 Contractor: Batzer Inc. Const. www.batzerinc.com

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
$12,960,000 $2,516,789
Click here to see the monthly expenditures report.


Project Description & Status :

Project: Status
Neighborhood Construction Information Meeting Complete
Remove and replace diseased trees or trees in direct conflict of construction Complete
Value engineering the architect's schematic design Complete
Demolition of selected areas Complete
Documents prepared for hard bid  Complete
Project will include renovation of 1949 Addition.  Cafeteria will be kept also. 2008-2010
Construction Fall 2008-Dec. 2009


PROJECT PHOTOS:

Jackson South Elevation
 Jackson Southeast Elevation Jackson East Elevation

Preliminary gym area

Looking west

Looking North East

   
   