Kennedy Elementary School

All projects complete.


 
PROJECT SUMMARY:

Kennedy Elementary was built between 1977-1982 and features 28 classrooms on its 10 acre campus.  This project included new roofing, heating/ventilation and air conditioning upgrades, new security upgrades, flooring and site work.

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: MSD www.medford.k12.or.us
 Architect: MSD www.medford.k12.or.us

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-6/30/08
$2,264,853 $2,329,079
Click here to see the monthly expenditures report.
Due to the closing out of the fiscal year, new total expenditures through September 08 will be reported mid-October.


Project Description & Status :
Project: Status
Roofing Complete
HVAC upgrade Complete
Security Complete
New flooring Complete
Site Work Complete


PROJECT PHOTOS:

Old roof


New roof
 

HVAC upgrade during installation

Exterior painting

New flooring

Superintendent Phil Long at ribbon cutting