Lone Pine Elementary School

Estimated Construction Dates: Summer 2008-Fall 2009
Last Updated on 9-19-08


PROJECT SUMMARY:                                                                                        © David Gibb Photography

Lone Pine Elementary School was built in 1926 and has had several remodels/additions to its current 30 classrooms on 10 acres.  This project will have new construction built and the existing classroom wings and media center will be renovated.  A new classroom and administration building will be built  connecting to the existing classroom wing.  The gym/commons area will be demolished and replaced with a new gym/commons/kitchen and cafeteria building.  The two upper classroom buildings with be renovated with new heating, ventilation, air conditioning, flooring, paint and more.
The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

Click here to view the architect's drawings of the new Lone Pine Campus
(The <01, <02, <03 markings on the map are the points of view of the 3 perspectives. Dotted lines represent covered walkways)

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: Jim McNamara
McNamara Engineering
 
 Architect: Mahlum Architects www.mahlum.com
 Contractor: Adroit Construction www.adroitbuilt.com

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-6/30/08
$15,759,572 $1,436,933
Click here to see the monthly expenditures report.
Due to the closing out of the fiscal year, new total expenditures through September 08 will be reported mid-October.

Project Description & Status :
Project: Status
Construction Information Meeting
View the meeting presentation at http://www.medfordschooldistrict.org/pmpresentations.htm
Complete
Security upgrade Complete
Hazardous material removal Complete
Demolish original school building Complete
Set up modular classrooms for temporary facilities during construction Complete
Renovate lower floor of media center with a temporary school office Complete
Renovate student restrooms Complete
Demolish buildings on north side of campus (Gym, Admin and Cafeteria) Complete
Reconstruct site utilities including electrical, natural gas, water service, phone/data, intercom, fire alarm Complete
Fence construction site so that work can occur during school year without student disruption Complete
Build new gym, commons, kitchen and cafeteria building 2008-2009
Build new administration and classroom building 2008-2009
Renovate the two upper classroom wings Summer 2009

PROJECT PHOTOS:

Temporary office in lower level



Modular units set up as temporary space.

Set up classroom




 

New Page 2