Oak Grove Elementary was built in 1891 and has had several additions and remodels.  The school has 19 classrooms on its 10 acre campus.  Renovation and new construction will be developed based on Architect's evaluation.

Click here to take a virtual tour of the new construction and renovation designs

Oak Grove Floor Plan

Oak Grove Site Plan 2008-2009 School Year

The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: Jim McNamara
McNamara Engineering
 
 Architect: Opsis/Abell Architects www.opsisarch.com 
www.abellarchgroup.com
 Contractor: Adroit Construction www.adroitbuilt.com

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-1/31/09
$9,650,000 $5,877,862
Click here to see the monthly expenditures report.

Project Description & Status :
Project: Status
Construction Information Meeting
View the meeting presentation at http://www.medfordschooldistrict.org/pmpresentations.htm
Complete
Moved playground over to alternative location for construction Complete
Security upgrade Complete
Demolish current gym Complete
Reconstruct site utilities including electrical, water, sewer and storm drains Complete
New roofing and windows Complete
Renovate upper classroom buildings with new heating, ventilation, air conditioning, windows and finishes.  17 classrooms total Complete
Renovate the original school building In progress
Construct a new gym/admin building In progress
Renovate the cafeteria and north classroom building. Summer 2009
Complete outdoor teaching space, landscaping and refinish parking lot 2009


PROJECT PHOTOS:

Front approach



Temporary office

Preparing to pour footings

Clean up after gym demolition

New walkway eaves