Roosevelt Elementary

Estimated Construction Dates: Summer 2008-2009
Last Updated on 9-19-08


 
PROJECT SUMMARY:                                                                                       

Roosevelt Elementary was built in 1911 and has 29 classrooms on its 4.5 acre campus.  The school will be renovated and new construction of the Roosevelt school, built in 1911.  Full scope of work will be developed based on Architect's evaluation and design.  Design documents will be finalized in early summer.

View Opsis/Abell School Board Presentation 1-8-08

View drafted floor plans for the new building

Limited Exterior Masonry Assessment--Roosevelt Elem 4-15-08


PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: Bush Consulting Services LLC 541-830-0922
 Architect: OPSIS/Abell Architects www.opsisarch.com
www.abellarchgroup.com
 Contractor: Batzer Construction www.batzerinc.com

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-6/30/08
$12,000,000 $1,108,236
Click here to see the monthly expenditures report.
Due to the closing out of the fiscal year, new total expenditures through September 08 will be reported mid-October.


Project Description & Status :
Project: Status
Neighborhood Construction Information Meeting Complete
Remove and replace diseased trees or trees in direct conflict of construction Complete
Value engineering the architect's schematic design Complete
Demolition of selected areas Complete
Documents prepared for hard bid  Complete
Construction Fall 2008-Dec. 2009
Out to bid/bid acceptance process Complete


PROJECT PHOTOS:

Architect rendering



 

New Page 2