Wilson Elementary School

Construction Dates: June 2008-Winter 2008
All projects completed

PROJECT SUMMARY:                                                                                    

Wilson Elementary School was built in 1958 and has 25 classrooms on its 11 acre campus.  It will undergo renovations including new roofing, heating & ventilation and air conditioning upgrade, improved security, new flooring, window replacement, interior and exterior painting.  By upgrading the heating & ventilation and installing flooring instead of carpet, classrooms will have less allergens while contributing to better air quality for students.  Flooring is also found to last 30-40 years instead of carpet which lasts 10-15, and is easier to maintain.
The Medford School District advertises requests for proposals (RFPs) at http://www.medford.k12.or.us/RFP.asp?SectionID=140

 
PROJECT TEAM:
Capital Project Manager: Medford School District www.medford.k12.or.us
 Project Manager: Todd Liles MSD www.medford.k12.or.us
 Architect: MSD www.medford.k12.or.us
 Contractor: TBA Bid 2008

Project Budget and Current Expenditures:
 
Project Budget
 
Current Total Expenditures
2/1/07-6/30/08
$2,987,734 $1,121,649
Click here to see the monthly expenditures report.
Due to the closing out of the fiscal year, new total expenditures through September 08 will be reported mid-October.

Project Description & Status :
Project: Status
Construction Information Meeting
View the meeting presentation at http://www.medfordschooldistrict.org/pmpresentations.htm
Complete
Security upgrade Complete
Cafeteria paint and new flooring Complete
Gym paint Complete
Paint interior & exterior Complete
New caroentry with computer stations in most classrooms Complete
Upgraded bathroom facilities Complete
Breezeway Reconstruction Complete
New roofing Complete
Heating, ventilation and air conditioning upgrade Complete
New flooring Complete
Windows and blinds replacement Complete


PROJECT PHOTOS:

New gym paint

New cafeteria flooring

 
New office carpentry

New computer desk carpentry

Old restrooms

Renovated restrooms

   